The “sixty day rule” (MN Statute 15.99) does not apply to projects that are going through the environmental review process. Because environmental review decisions can often take months (and in some cases years) to be reached, environmental review is one of the exceptions to the rule. The clock stops ticking on the “sixty day rule” until environmental review has been completed and, once environmental review has been completed, the clock is reset at 60 days.